Level 4 155 Wickham Terrace, Spring Hill QLD 4000

Sewerage Treatment Plant Upgrades & Decommissioning Works

The University of Queensland
Project details

Project Name
Sewerage Treatment Plant Upgrades & Decommissioning Works

Client
The University of Queensland

Budget
$7m

Role
Superintendent

Gripfast were engaged to superintend the D&C Contract for their new Gatton Sewerage Treatment Plant project.

The project includes the decommissioning of the existing plant and equipment under strict heritage requirements.

Contract – D&C

Inclusions:
  • Wastewater Treatment Plant Amenities Building
  • Chlorine Dosing Building and associated Equipment
  • Car Parks and Access Roads
  • Pumping Station
  • Fencing
  • Decommissioning of existing STP