Woorabinda Indigenous Councils Critical Infrastructure Program

Project Name
Woorabinda Indigenous Councils Critical Infrastructure Program
Client
DLGRMA and Council
Budget
$1.4m
Role
Project Manager
Working with council, Gripfast managed the delivery of critical water, wastewater and solid waste infrastructure to the community.
The project involved constructing a new treatment plant and sewerage storage ponds, relining the community’s sewerage network, an upgrade to four sewerage pump stations and the installation of a 20Ha irrigation system to irrigate recycled water from the treatment plant. The project ran incident free for two years and was delivered on time and under budget.
Inclusions:
- Waste Water Treatment Plant
- Upgraded to 4 Pump Stations
- Sewerage Storage Ponds
- Water Supply and Treatment Upgrades (including SCADA)
- Support of and engagement with local community